ECRL construction progress ahead of target
PARLIAMENT | Construction of the East Coast Rail Link (ECRL) project continues to advance beyond its original target, said Deputy Transport Minister Hasbi Habibollah.
Hasbi said as of Nov 30, the overall construction of the project achieved actual progress of 19.69 percent compared to the original schedule of 18.78 percent.
He said for Section A from Kota Bharu to Dungun which includes the construction of six stations namely Kota Bharu, Pasir Putih, Jerteh, Bandar Permaisuri, Kuala Terengganu and Dungun, physical work...